It will last 21 days/ Tomorrow the works start on the Fushë Krujë-Thumane axis, how will the movement of vehicles be diverted

2023-05-22 19:03:06Aktualitet SHKRUAR NGA REDAKSIA VOX
It will last 21 days/ Tomorrow the works start on the Fushë
Illustrative photo

The next day, Tuesday, the intervention for the rehabilitation of the asphalt layers on the Fushë Krujë-Thumane road axis will begin.

The works will last for 21 days and through an announcement, the Albanian Road Authority has informed the drivers of how traffic will be diverted.

NOTICE:

Within the framework of the maintenance contract, tomorrow, 23.05.2023, the intervention for the rehabilitation of the asphalt layers in the Fushë Krujë-Thumane segment begins

According to the Traffic Management Plan, as well as the placement of information boards for each diversion, drivers will be oriented on the route they will follow.

The work will be carried out in partial segments, with alternative road diversions, in order not to disrupt traffic flow.

The works will last 21 days as follows

• The first 4 days will be worked on the segment Kryqëzim Luz-Kryqëzim Borizane, where the direction of movement Tirana-Milot will circulate via the alternative route in the segment Kryqëzim Luz-Kryqëzim Borizane-Kryqëzim Borizane.
• Starting from the fifth day to the sixth day, the work will continue on the Borizane Intersection – Thumane Roundabout segment. Sensi Tirana - Milot will pass in the segment Kryqëzim Borizane - Center Borizane - Thumanë - Thumanë Roundabout. Then it will continue the normal movement in the direction of Milot.
• Starting from the seventh day to the ninth day, the work will continue in the Thumanë Roundabout-Borizane Intersection segment. Sensi Tirana-Milot will pass in the segment Kryqëzim Borizane-Cendre Borizane-Thumanë-Réthrotullimi Thumanë.
• Starting from the tenth day to the fourteenth day, work will continue on the Borizane Crossing-Luz Crossing segment. Sensi Tirana-Milot will move to the segment Kryqëzim Luz-Cendre Borizane-Kryqëzim Borizane.
• Starting from the fifteenth day to the seventeenth day, work will continue on the Y-Junction segment Luz. Sensi Tirana-Milot will pass in the segment Y Branch-Fushë Krujë-Ring-Kryqëzim Luz.
• Starting from the eighteenth day to the twenty-first day, work will continue on the segment Kryqëzim Luz-Y Branch. Sensi Tirana-Milot will move to the segment Y Branch-Fushë Krujë-Unazë-Kryqëzim Luz.

The Albanian Road Authority requests the understanding and the implementation of the provisional signage from the vehicle drivers regarding this deviation.